Budget, committed, actual, certified, paid: five different numbers.

Construction reports often put them in one column. Here is what each means, and why mixing them leads to bad decisions.

A client looks at a report, sees UGX 3.6 billion against the road, and assumes it has been paid. A contractor sees the same figure and thinks there is still plenty of budget. Both are wrong, because the figure is the actual cost so far, which is neither the payment nor the remaining budget.

Budget

The approved amount for a piece of work, usually from the BOQ or estimate. It is a plan. Nothing has been spent.

Committed

Money promised through approved purchase orders and subcontracts. It has not been paid, but it is no longer free to spend. Free budget is budget minus commitments, not budget minus payments.

Actual cost

The cost of goods and work received: invoices matched to a delivery, and approved labour and plant records. It is a liability to the supplier, not yet a payment.

Certified

On measured contracts, the engineer or QS certifies the value of work done in a valuation or interim payment certificate. Certified is what the employer has agreed it owes, usually less retention.

Paid

Paid means the money left the account. Civil 360 separates paid, awaiting bank (a transaction ID was entered) from paid, confirmed (matched to the bank or mobile-money record). A receipt photo or SMS is evidence, not proof of settlement.

One cost code, five different figures

Demonstration data

BOQ 4.02 Subbase, UGX millions. Step through what happens to it.

BudgetThe approved amount for the work. Not money spent.
1,120
CommittedPromised through approved orders and subcontracts. Still unpaid.
0
Actual costGoods or work received and invoiced. A cost, not yet a payment.
0
CertifiedMeasured and certified in a valuation or IPC.
0
Paid, confirmedMatched to the bank or mobile-money record. Only now is it settled.
0

Forecast

A useful forecast at completion for a cost code is actual cost, plus outstanding commitments, plus the estimate of what is still to be bought. When that exceeds the budget, the overrun is visible while there is still time to act.