A client looks at a report, sees UGX 3.6 billion against the road, and assumes it has been paid. A contractor sees the same figure and thinks there is still plenty of budget. Both are wrong, because the figure is the actual cost so far, which is neither the payment nor the remaining budget.
Budget
The approved amount for a piece of work, usually from the BOQ or estimate. It is a plan. Nothing has been spent.
Committed
Money promised through approved purchase orders and subcontracts. It has not been paid, but it is no longer free to spend. Free budget is budget minus commitments, not budget minus payments.
Actual cost
The cost of goods and work received: invoices matched to a delivery, and approved labour and plant records. It is a liability to the supplier, not yet a payment.
Certified
On measured contracts, the engineer or QS certifies the value of work done in a valuation or interim payment certificate. Certified is what the employer has agreed it owes, usually less retention.
Paid
Paid means the money left the account. Civil 360 separates paid, awaiting bank (a transaction ID was entered) from paid, confirmed (matched to the bank or mobile-money record). A receipt photo or SMS is evidence, not proof of settlement.